| Section | Description | Value (ex-GST) | % of sum |
|---|
Values are taken from Annexure 1 — Corrected Schedule 3, which is bound into the signed contract and
restores the 3,200 m of 560 PN10 line ($54,362.70) and corrects line 4.3 to 28 days ($298,145.40).
Line 6.4 Weather Standdown ($33,661.15) is excluded from the fixed price — it appears in the Comments
column only, and is treated as reimbursable if weather standdown occurs.
The Payment Certificate template confirms the order: "This payment certificate does not constitute a tax invoice. Payment will only be implemented on receipt of an original invoice."
| Claim | Claim date — editable cl. 26.2(a)(i) |
Certificate by cl. 26.3(a) |
Invoice cl. 26.3(d) |
Paid — limb (i) 30 days after EOM |
Limb (ii) cap 35 days after claim |
Watch |
|---|
Dates recalculate on WA Business Days (weekends and WA public holidays excluded). Claim dates save in this browser.
Each claim is valued at the lesser of the amount shown for that month in Schedule 3 and the value of the Works actually executed, less amounts previously claimed. Progress is measured line by line against the Schedule 3 schedule of values, using the Continuation Sheet in Schedule 8 — Forms and Templates:
| Column | Meaning |
|---|---|
| A / B | Item number and description of work — our Schedule 3 lines |
| C | Scheduled Value — the Schedule 3 amount for that line |
| D | Approved from previous claim |
| E | Application this period |
| F | Completed and stored to date |
| Total % | F ÷ C — percentage complete |
| G | C − F — balance to finish |
| Retention | Nil. Schedule 1 provides security as 2 × 2.5% bank guarantees, so no cash retention is deducted — DTL is paid the full certified value. |
Enter the anticipated claim value for each month. Figures are indicative and will be superseded by the value of Works actually executed at each claim date. Cumulative and balance calculate automatically. Values save in this browser.
| Claim | Claim date | Anticipated claim | Cumulative | % of sum | Balance to claim |
|---|
| Ref | Item |
|---|---|
| 26.2(b)(i) | Detailed breakdown of contract value executed — since Commencement and since the last claim — in a form agreed with the Principal Representative |
| 26.2(b)(ii) | Contract value of any Variation work executed and incorporated since the last claim |
| 26.2(b)(iii) | Amounts previously paid |
| 26.2(b)(iv) | DTL's estimate of cost to complete the Works |
| 26.2(b)(v) | Program status report, payment register and financial statement, in the form required by the Principal Representative |
| 26.2(b)(vi) | A pro-forma invoice |
| 26.2(b)(vii) | The purchase order number — 182113 |
| 26.2(b)(viii) | Any other information reasonably required by the Principal Representative |
| Trigger | Claim due within | Detail |
|---|---|---|
| Certificate of Completion final Separable Portion |
30 Business Days cl. 26.2(a)(ii)(A) |
Final account. If the certificate issues at Completion (20 Nov 2026), the claim is due by approximately 6 January 2027. Half the security (2.5%, $69,725.11) is released at Completion. |
| Expiry of the Defects Liability Period | 30 Business Days cl. 26.2(a)(ii)(B) |
DLP is 24 months from Completion — ending about 20 November 2028 (longstop 36 months). Claim due by approximately 1 January 2029. The remaining 2.5% ($69,725.11) is released here. This sits two years past the job and is the one that gets forgotten. |
| Item | Position |
|---|---|
| Security | 5% = $139,450.23, provided as 2 × 2.5% bank guarantees ($69,725.11 each). Half released at Completion, half at the end of the DLP. No cash retention. |
| Liquidated damages | $1,800 per day, capped at 5% ($139,450.23) — the cap is reached after 77 days of delay. |
| Payments on account | All payments are on account only (cl. 26.4) — payment is not evidence that the Works are complete or free of defects. |
| Unfixed materials | Not claimable unless agreed with the Principal, and then only against a separate bank guarantee (cl. 26.7). Relevant to the supply-heavy early claims. |
| Weather standdown | Excluded from the fixed price (Schedule 3, line 6.4) — reimbursable / dayworks if it occurs. |
| SOPA | The Building and Construction Industry (Security of Payment) Act (WA) applies (cl. 26.8) as the statutory backstop on payment. |
| Item | |
|---|---|
| 1 | Clause 26.3(e) — which payment limb governs. Confirm payment is due on the earlier 35-day longstop. Approximately one month of cash on every claim. |
| 2 | Claim breakdown format. Agree the form of the detailed breakdown under cl. 26.2(b)(i), and the form of the program status report, payment register and financial statement under cl. 26.2(b)(v), before the first claim. |
| 3 | Schedule 8 / Schedule 9 naming. The contract refers to Schedule 8 — Forms and Templates; the file issued to DTL is named SCHED 9. Confirm they are the same document. |
| 4 | Annexure 1 — Corrected Schedule 3. Confirm the corrected price schedule is the executed version, so Section 4 is claimed on the corrected basis. |